Clarify DRIs for expedited drafting (#28050)

This commit is contained in:
Noah Talerman 2025-04-09 16:07:23 -04:00 committed by GitHub
parent 6e70d44c61
commit c2663adcba
No known key found for this signature in database
GPG key ID: B5690EEEBB952194

View file

@ -121,8 +121,8 @@ You'll know it's time for expedited drafting when:
- A user story on the drafting board won't reach "Ready for spec" by the last estimation session in the current sprint and cannot wait until the next sprint. This can also happen when we decide to bring a user story in mid-sprint.
What happens during expedited drafting?
1. If the story has a requester, notify the requester. The customer DRI should confirm that the updated scope still meets the requester's need.
2. If the user story wasn't "Ready for spec" by the last estimation session, the product group's engineering manager (EM), [release DRI](https://fleetdm.com/handbook/company/communications#directly-responsible-individuals-dris), and Head of Product Design are notified in the `#g-mdm`, `#g-orchestration`, `#g-software` Slack channel. Decision to allow the user story to make it into the sprint is up to the release DRI.
1. If the story has a requester, notify the [customer support DRI](https://fleetdm.com/handbook/company/communications#directly-responsible-individuals-dris). The customer support DRI should confirm that the updated scope still meets the requester's need.
2. If the user story wasn't "Ready for spec" by the last estimation session, the product group's engineering manager (EM), [DRI for what goes in a release](https://fleetdm.com/handbook/company/communications#directly-responsible-individuals-dris) (release DRI), and Head of Product Design are notified in the `#g-mdm`, `#g-orchestration`, `#g-software` Slack channel. Decision to allow the user story to make it into the sprint is up to the release DRI.
3. If the user story is already in the sprint, the EM, QA, release DRI, and Head of Product Design are notified in the `#g-mdm`, `#g-orchestration`, `#g-software` channel. If there are significant changes to the requirements, then the user story might be pushed to the next sprint. Decision is up to the release DRI.
4. If the release DRI decides the user story will be worked on this sprint, drafts are updated or finished.
5. UI changes [are approved](https://fleetdm.com/handbook/company/development-groups#drafting-process), and the UI changes are brought back into the sprint or are estimated.